Quantitative Aptitude – Time and Work – John takes twice as much time as Jack to finish
Slot – 2 – Quantitative Aptitude – Time and Work – John takes twice as much time as Jack to finish
Q. John takes twice as much time as Jack to finish a job. Jack and Jim together take
one-thirds of the time to finish the job than John takes working alone. Moreover, in
order to finish the job, John takes three days more than that taken by three of them
working together. In how many days will Jim finish the job working alone? Answer: 4
Solution:
Let the time taken by Jack to complete the work alone is x so that of taken by John alone = 2x
Let Jim takes y days complete it alone so as per question,
2x/3 = (x*y)/(x+y)
2x +2y = 3y
y = 2x
also it is given that
John takes three days more than that taken by three of them working together
So one day work for them
1/x+1/2x +1/2x = 4/2x = 2/x
Combined time for all three = x/2
Thus 2x – x/2 = 3
Or x = 2
Thus required time for Jim = 2x = 2*2 = 4
a) 1000+ Videos covering entire CAT syllabus b) 2 Live Classes (online) every week for doubt clarification c) Study Material & PDFs for practice and understanding d) 10 Mock Tests in the latest pattern e) Previous Year Questions solved on video