When they work alone, B needs 25% more time to finish a job than A does. They two finish the job in 13 days in the following manner: A works alone till half the job is done, then A and B work together for four days, and finally B works alone to complete the remaining 5% of the job. In how many days can B alone finish the entire job?

a) 22

b) 18

c) 20

d) 16

Solution:

ratio of time taken by A and B to complete the work alone = 1: 1.25 = 4x : 5x

As A complete half of the work alone  and B complete 5% of the work alone, so they will complete remaining 45% of work in 4 days .

So time taken by them to complete the whole work together = 4 * 100/45 = 80/9

Or (4x*5x)/(4x+5x) = 80/9

x = 4

Thus time taken by B to complete the work alone = 5x = 20 days

correct answer c) 20

Other posts related to Quantitative Aptitude – Modern Maths

Permutation and Combination – Fundamental Principle of Counting
Permutation and Combination – Distribution of Objects
How to find Rank of a Word in Dictionary (With or Without Repetition)
Set Theory- Maximum and Minimum Values
How to solve questions based on At least n in Set Theory for CAT Exam?
Sequence and Series Problems and Concepts for CAT 2017 Exam Preparation
Basic Probability Concepts for CAT Preparation

Online Coaching Course for CAT Exam Preparation

a) 750+ Videos covering entire CAT syllabus
b) 2 Live Classes (online) every week for doubt clarification
c) Study Material & PDFs for practice and understanding
d) 10 Mock Tests in the latest pattern
e) Previous Year Questions solved on video

Know More about Online CAT Course

Leave a Reply

Your email address will not be published. Required fields are marked *